Standards, qualification and certification

📍 Where we are: Part IV · Making It Real — Chapter 14 of 15. Chapter 13 described how a part is inspected. This chapter explains the rules those checks are measured against and how a part, a process and a company earn trust.

The simple version

Think of a restaurant. A tasty dish is not enough to be allowed to serve it to the public. The kitchen is inspected, the ingredients are traced, the cooks are trained, and the recipe is followed the same way every night. Qualification in AM is the same idea: it is not only "this part is good" but "this machine, this recipe and this team make good parts every time, and we can prove it." Standards are the shared rulebook, and regulators decide how strict the rulebook must be for a given use.

What this chapter covers​

We look at who writes AM standards, name the main ISO/ASTM documents and what each one is for, and explain the layers of qualification: material, machine, process and part. Then we sketch, at a high level, how aerospace, space and medical sectors add their own requirements. We keep the running bracket in mind: the same bracket needs very different evidence depending on whether it holds a lamp or an aircraft engine accessory. This is an orientation, not legal or certification advice; the standards themselves are paywalled and should be read in full before relying on them.

Who writes the standards​

AM standards come mainly from two bodies working together. ISO/TC 261 and ASTM Committee F42 cooperate under a partnership agreement signed in 2011, aiming at "dual logo" ISO/ASTM standards with international consensus [1]. The committees describe a three-tier structure: general top-level standards, standards for specific materials or processes, and specialised standards for particular needs [1]. Industry bodies and agencies add their own documents on top, such as NASA and aerospace regulators. A widely cited overview argues that, for flight-critical parts, standards alone are not enough: qualification and certification also need process, microstructure and fracture modelling tied to component life prediction [2].

The key documents​

The table lists a few that readers meet first. Edition years were checked against the publisher pages.

DocumentWhat it is for
ISO/ASTM 52900:2021, General principles — Fundamentals and vocabularyShared terminology, including the seven process categories used throughout these books [3]
ISO/ASTM 52902:2023, Test artefactsBenchmark shapes to assess a machine's geometric capability (see Quality, inspection and non-destructive testing)
ISO/ASTM 52904:2024, Process characteristics and performance, metal PBF for critical applicationsOperation and production control of metal powder bed fusion where failure leads to immediate threats [4]
ISO/ASTM 52909:2024How to report orientation and location dependence of mechanical properties
ISO/ASTM 52920:2023, Qualification principles — Requirements for industrial AM processes and production sitesRequirements added on top of a quality management system for AM production [5]
ISO/ASTM TS 52930:2021, Qualification principles — Installation, operation and performance (IQ/OQ/PQ) of PBF-LB equipmentMachine-focused qualification for laser powder bed fusion [6]
ISO/ASTM 52941 (2020; 2026 edition retitled System performance and reliability tests…)Machine acceptance and requalification tests for laser powder bed fusion in aerospace [7]
ASTM F3301Specification for thermal post-processing of metal powder bed fusion parts (see Post-processing)

ISO/ASTM 52920 is independent of material and manufacturing method and is meant to sit on top of an existing quality management system such as ISO 9001 or EN 9100 [5]. ISO/ASTM TS 52930 is a Technical Specification, not a full standard, and does not cover feedstock qualification or post-processing beyond powder removal [6]. A counterpart for electron beam powder bed fusion exists as ISO/ASTM TS 52949:2025 [6]. Material specifications also exist, for example ASTM F2924 for Ti-6Al-4V made by powder bed fusion [8].

The layers of qualification​

It helps to separate four questions. This framing is a teaching aid; each standard organises the details in its own way.

  1. Material. Is the powder or feedstock within specification, and is it traced from lot to lot? Material specifications such as ASTM F2924 define composition, microstructure and minimum properties [8].
  2. Machine. Is the machine installed correctly, operating within limits, and performing repeatably? These are installation qualification (IQ), operational qualification (OQ) and performance qualification (PQ). IQ is objective evidence that the installed equipment meets the manufacturer's approved specification [6]. ISO/ASTM 52941 adds measurable tests such as laser power, beam position and scanning speed [7].
  3. Process. Does the whole chain, from file to finished part, give the same result each time? ISO/ASTM 52920 distinguishes qualification that is part-specific (the process is tuned to the part, as in serial production of one part) from process-generic (parts are adjusted to what the process can do) [5].
  4. Part. Does this specific part meet its requirements? Parts are often classified by the consequence of failure. NASA-STD-6030 classes parts as A, B or C, and ties requirements to class [9].

A four-layer stack from material through machine and process up to part, with example standards on each layer and three sectors, aerospace, medical and space, that add their own rules on top. Qualification builds from the bottom up, and each sector adds its own rules on top of the common layers. Original diagram by the authors, created with AI assistance.

Requalification. A qualified setup is not permanent. ISO/ASTM 52920 says changes such as hardware, firmware, power source, repair, relocation and feedstock specification should each be evaluated for the need to requalify [5]. This is why a "small" software update can trigger paperwork.

Sector pathways at a high level​

Aerospace. EASA's certification memorandum CM-S-008 (Issue 04) gives guidance on EASA expectations for metallic and non-metallic AM and adds guidance on early engagement with the agency and on low-criticality parts (classes C and D), which need a conservative justification of that classification [10]. In the US, FAA Advisory Circular AC 33.15-3 (June 2023) describes one acceptable, non-mandatory way to show compliance with 14 CFR 33.15 for aircraft engine parts made by powder bed fusion [11].

Space. NASA-STD-6030, approved 21 April 2021, sets 115 verifiable "shall" requirements for AM flight hardware. It is built around an AM Control Plan, a quality management system, a material properties suite and part classification [9].

Medical. The FDA's guidance Technical Considerations for Additive Manufactured Medical Devices (final, 5 December 2017) covers design, software workflow, material control, build, post-processing and testing. AM devices are generally expected to meet the same regulatory requirements as any device of their class, and FDA encourages the Pre-Submission process when unsure what to include [12]. The page now notes that it predates a later quality system regulation, so check the current rules.

Our bracket. For a consumer product, the buyer typically asks for far less: a supplier with a sound quality system and routine checks. For an aircraft-engine bracket, expect part classification, a qualified machine and process, controlled material, a defined post-processing chain, inspection of every part or a sample, and records for each. The geometry could be the same; the evidence is not.

Why it matters​

AM makes parts whose properties depend on the process, so you cannot simply buy a "material" and trust the part. Qualification replaces trust in a datasheet with evidence from your own machine and recipe. It is also the largest time and cost barrier for regulated AM, which is why it is a major topic in Book 4.

In the real world​

Large buyers write supplier requirements on top of the standards above, and regulators issue project-specific agreements. Both EASA and the FAA encourage early engagement on AM projects [10], so the practical first step is often a conversation, not a test.

Key terms​

  • ISO/ASTM 52900 — the AM vocabulary standard that defines the seven process categories.
  • ASTM F42 — the ASTM committee on additive manufacturing technologies, which co-develops ISO/ASTM standards with ISO/TC 261.
  • Qualification — gathering and documenting evidence that a material, machine, process or part meets stated requirements.
  • IQ / OQ / PQ — installation, operational and performance qualification of equipment.
  • Part classification — grouping parts by the consequence of failure so that requirements scale with risk.
  • Requalification — repeating some qualification after a change to the machine, software, material or site.
  • Technical Specification (TS) — an ISO document type published at a less mature stage than a full International Standard.
  • Certification — a regulator's approval that a product or design meets the rules for its use.
  • AM Control Plan — the NASA-STD-6030 document that, with a quality system, forms the backbone of AM production control.
  • Pre-Submission — an FDA process for asking about expectations before filing a device application.

Where this leads​

With the whole chain in view, from process to post-processing to proof, the last chapter helps you choose: Choosing a process: a decision guide.